A cross section of recent projects

 

 

 
 
Project: Three Evaporators ex Hamilton to Chinchilla Queensland
  Project involved the Door to door movement of three Evaporators ex Hamilton to Chinchilla Queensland.  
  The Trans Tasman leg was via Roll on Roll of shipping.  
  With the Cunningham Highway being out of use due to the Queensland floods the Warrigal Highway had to be utilized.
This alternative route had a height restriction of 5.4m and to keep within this allowance one end of the Evaporator was bookend ensuring the erection program schedule was maintained.
Each Evaporator measured 31m x 5.5m x 5.0m and weighted 100 tonnes.
 
Project: Mahinerangi Wind Farm
 

The Project involved road transport of 12 wind turbines and all support equipment from Port of Dunedin to the Mahinerangi Wind Farm site 70 km South West of Dunedin.

Turbine components began arriving at the Port during December 2010/ January 2011.
 
     
 

Main components:

  • 36 towers up to 28.5m x 4.1m x 4.1m - each weighing up to 76 tonne
  • 36 blades 44.5m x 3.2m x 3.6m - each weighing 12 tonne
  • 12 Nacelles - each weighing 80 tonne
  • 12 ISO container loads of support equipment
 
     
 

Responsibilities included:

  • Discharge from heavy lift ships hook and movement to a temporary wharf storage site.
  • Progressively transporting all the equipment from the Port area on custom designed trailer equipment
  • Logistics working with local council and NZTA closing the Dunedin Motorway on specified periods five days per week for the over dimensional loads
  • Receive and discharge all components at the project site and handle through to positioning for final installation.
 
Project: Shipment of two 140 tonne boilers Thailand to Australia  
  This project included transport of the two boilers from the inland fabrication plant to the Port at Mat Ta Phut, loading on board and shipping to Australia.  
  The Thailand road transport was via a complex route and involved three days due to the load height approaching 7.0m.  
  At 140 tonnes each the boilers were too large to unload direct at Port Kembla and they were discharged at a private berth close to their final location then trucked to the site.
The Globaltrans scope of work included all charter arrangements of the specialised heavy lift ship.
 
Project: Te Uku Wind Farm
Te Uku Wind Farm  

The Project involved 28 wind turbines from Port of Auckland for transport to Te Uku Wind Farm 270 km South West of Auckland.
Turbine components began arriving at the Port during September 2010.

 
Te Uku Wind Farm  

Responsibilities included:
Discharge from heavy lift ships hook and movement to a temporary wharf storage site.
Progressively road transport all cargo through the city of Auckland to the Project site.
Receive at site and handle through to final installation.

 
Te Uku Wind Farm  

Main components:
84 blades 49.5m x 3.2m x 3.6m each weighing 15 tonnes
84 towers up to 36m x 4.2m  x 4.2m  each weighing 56 tonnes
28 Nacelles each weighing 85 tonnes
80 ISO container loads
75,500 cubic tonnes of loose stow support equipment

 
Te Uku Wind Farm  

Additional work Scope included:
Leasing 15,500sqm  of hard stand and at the Port site.
Preparing all components for road transport.
Arranged with local council on route to raise an overhead bridge to a permanent new height to allow all loads to travel on a more direct route between Port and project site.

 
Project: Thailand to Australia
  This international project involved three large Boiler modules being uplifted from the fabricators production plant in Thailand and delivered to the installation site in Melbourne Australia. Due to the height restrictions between Port Melbourne and the final destination, the main Furnace section was transported by road in ‘bookends’ to keep within a maximum height of 5.4m.  
  The project was 2.5 years in the complex transport planning process. The Furnace section from fabricators to the loading Port in Thailand was carried out over a three day period. In Australia the inland delivery to Coolaroo was completed over two nights.  
 

Dimensions

Furnace section              22.0m x 6.5m x 5.2m           110 tonnes
Generating Bank            11.5m x 7.7m x 3.8m             68 tonnes
Economiser module       10.4m x 5.5m x 3.6m             45 tonnes

 

 

 
Project: New Auckland Lion Nathan Brewery
 

Global Transport handled the over dimensional transport contract for the movement of 29 Fermenter Tanks from NDA in Hamilton to the South Auckland Site.

 
  The majority of the Tanks weighed from 15 to 20 tonnes each with dimensions up to 20m x 5.3m x 5.3m  
     
 

Upon arrival at the $250 million development the Tanks were lifted off using two cranes and then positioned upright and secured in their final location.

 
Project: Baghouse
 

This Project involved transporting 5 modules (Bag Houses) moved by a combination of Road transport and Sea freight from Hamilton to Fonterra Edendale. Each unit weighed 20 tonnes and measured 16.2m x 6.2m x 6.2m.

 
  The haul route involved a 1840km journey from load out to destination.  
  One ship was loaded using its own heavy lift equipment and the second ship loaded using the berths container crane.  
Project: Cheddamaster from New Zealand to Ireland  
 

This project included uplifting three large machines from the Hamilton manufacturing plant  through to delivery on-site in Ballineen Ireland. The work scope covered road transport, ocean freight, all lifting and lashing arrangements plus supply of the equipment for ship loading and discharge.

Machine (1) 14.0m x 3.6m x 4.4m 16t

 
  Machine (2) 13.2m x 3.6m x 4.3m 12t  
  Machine (3) 12.7m x 3.6m x 2.7m 7t  

Project: Synlait Boiler from Thailand to New Zealand

 
 

Dimensions 11.5m x 7.5m x 5.0m weighing 75 tonnes.

This was a logistical challenge due to the center of gravity running in two diverse directions. The project included loading at the works in Thailand and deliver to position alongside foundation works at the Synlait site in New Zealand.

 
 

Due to height restrictions in Thailand the road transport operation between the plant and port load-out site required 20 hours additional hauling time negotiating low bridges and overhead wires.

Global Transport also supplied all the loading and unloading spreader beams and wires.

 

Project: Refinery Vessel shipped by Barge from NZ to Australia. View video of this project here

 

‘Stripper’ Refinery Vessel weighing 310 tonnes and measuring 40m x 7m x 7m manufactured by Fitzroy Engineering New Plymouth for Shell Oil Australia. The Project scope included the New Plymouth lead-out and discharge operations in Sydney. It also involved moving a smaller vessel and a range of supporting equipment.

 
  Vessel at Port Taranaki New Plymouth and loading onto the Barge.  

 

Barge approaching and passing (with minimal clearance) under the Parramatta River Bridge in Sydney.

 
 

 
Project: Shipping non-mobile heavy machinery.
  This Project included the shipment of large over dimensional machinery from inland
South Island New Zealand to Australia. As Australian quarantine regulations would
not allow entry of the tyres, it was therefore necessary to remove the wheels, leaving
the logistical problem of transportation.
 
Project: Shipping of 'Coal Reclaimer' ex Westgate to Newcastle.
  Another winning transport solution. This project involved land and barge transportation
of a 1000 tonne coal
reclaimer to a complex location requiring discharge from the barge to land alongside a river.
 
Project: Transportation of a complete Power Station from New Zealand to Melbourne Australia.
  This 5000m3 shipment involved all land transportation in New Zealand, packing,
ship loadout and discharge in Australia
.
 
Project: Pharmaceutical Tanks.
  Movement of 24 large pre-assembled units from Hamilton New Zealand to Singapore
through to foundation. Each unit measured 10m x 5.2m x 5.2m.
 
Project: Transformer load out Santos Brazil.
  Scope involved one 180 tonne and one 136 tonne units delivered to two New Zealand
destinations,up onto foundations.
 
Project: Shipment 15,000t Europe to Australia
  Transport of boiler 80t from foundation to ships hook Frederica Demark part of total shipment of 15,000t for Gladstone Australia  
  Loading of column at Frederica part of the above shipment dims 53m x 7m x 7m 205t  
Project: Ship charter incl Heat Exchangers Hamilton to West Australia
  Door to door shipment of two heat exchanges 25m x 6m x 6.1m 137t ex Hamilton to Ravensthorpe WA including ships charter.  
Project: 86t furnace NZ to West Australia
  Door to door movment of Furnace 86t ex New Plymouth to Ravenstorpe WA including ships charter  
Project: Shipment of a Brine Concentrator from Client Premises in Hamilton NZ to foundation in Bayswater, NSW, Australia  
  The Work scope included transport and shipment of two other vessels being moved with the Concentrator. Due to height restrictions on the haul route from New Castle, special transport saddles were fitted to the large Concentrator. This allowed the height to be reduced for the inland transport. Dimensions were 26.3m x 5.4m x 5.4m with a weight of 66t.  
 
Project: China to South America - 'Heat Exchangers', 'A Door to Foundation' Contract  
  Together with arranging the ship charter the Scope of this Project included both road transport in China and South America.
Dimensions - Heat exchanger (1) 17.5m x 4.0m x 4.0m weighing 54t
Heat exchanger (2) 19.2m x 4.0m x 4.0m weighing 67t.

Heat Exchangers
–Transporting under one of several low bridges on the haul route between the fabricator and Shanghai Port in China. The contract included challenging work conditions with this bridge allowing a clearance of just 75mm.
 
 
  Loading the first of the two Heat exchanges being shipped from China to Unidad Peru in South America..
 
  Discharge operations underway at Port Callao Peru.  
 
  Discharge from ship at Port Callao and preparing for haulage to Unidad out side of Lima.  
 
 
 
 
 
Other Projects